A project to modernize the terminal at Birmingham's airport is about two-thirds complete.
Al.com reports (http://bit.ly/UejcJD) that Tom Wesley of Birmingham's airport authority provided board members with an update on the project this week.
He said the airport authority has spent 67 percent of the $201.6 million allotted for the entire two-phased project at Birmingham-Shuttlesworth International Airport.
Authorities say the project will mean more amenities for passengers and also bring the airport in line with post-Sept. 11 security standards.
Demolition and reconstruction on the first phase, involving concourses A and B, began in June 2011.
Airport spokeswoman Toni Herrera-Bast said the second phase involves the demolition and renovation of Concourse C. It will begin once the other concourses open this spring and should be complete in 2014.
___
Information from: The Birmingham News, http://www.al.com/birminghamnews